This documents related to 2021-09, the Eclipse Foundation's multi-project Simultaneous Release of September 2021.
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release |
Date |
Span |
Due dates |
Notes |
---|---|---|---|---|
2021-09 M1 |
Friday, July 16, 2021 |
07/09 to 07/16 |
|
3 weeks from 2021-06 GA |
2021-09 M2 |
Friday, August 6, 2021 |
07/30 to 08/06 |
3 weeks from M1 |
|
2021-09 M3 |
Friday, August 27, 2021 |
08/20 to 08/27 |
|
3 weeks from M2 |
2021-09 RC1 |
Friday, September 3, 2021 |
08/27 to 09/03 |
|
1 week from M3 |
2021-09 RC2 |
Friday, September 10, 2021 |
09/03 to 09/10 |
1 week from RC1 |
|
Quiet period |
09/10 to 09/14 |
No builds during "quiet period". It is assumed all code is done by the end of RC2. |
||
2021-09 GA |
Wednesday, September 15, 2021 |
|
5 days from RC2 |